[ARCHIVED] 10-30-2023 Update - Road Milling and Paving

Road improvements road sign

PSE&G has completed the gas main upgrades in several neighborhoods.  Now that the ground has settled, they will begin to restore roads with permanent paving.  Please see below for the milling and paving schedule.  This schedule will be adjusted in the event of inclement weather.

The milling and paving activities will occur during daytime hours between 7:00 a.m. and 6:00 p.m.  Work is scheduled to begin in the next couple of weeks, weather permitting. Please abide by all emergency “No Parking” signs, as they will be posted 24 hours before work is scheduled to begin on each street.

The goal is to complete this work with minimal impact to your neighborhood.  Police will be directing traffic, and residents will be able to drive on the roads during non-paving hours.

PSE&G is continuing to work on the roads.  Please see their website for updates.  They will notify residents before they begin working on your street.

    October 18th - Milling 

o    Surrey Lane - COMPLETED

o    Darby Court- COMPLETED

o    Salt Brook- COMPLETED


    October 19th - Milling

o    Charnwood Road - COMPLETED

o    Edward Court - COMPLETED

o    Crescent Drive - COMPLETED

o    Livingston Ave - COMPLETED


    October 20th - Milling

o    Livingston Avenue- COMPLETED

o    Central Avenue- COMPLETED


    October 23rd - Milling

o    Central Avenue- COMPLETED

o    Stoneridge- COMPLETED


    October 24th 

o    Milling

    Southgate/Ryder Way - COMPLETED

 
    October 25th

o    Milling

    Southgate/Ryder Way - COMPLETED


o    Paving

    Edward Court - COMPLETED

    Park Place - COMPLETED

    Livingston Avenue - COMPLETED

    Surrey Lane - COMPLETED

    Darby Court - COMPLETED

    Salt Brook - COMPLETED

    Charnwood Road -- COMPLETED

    October 26th

o    Milling

    Possum Way- COMPLETED

    Southgate/Ryder Way- COMPLETED

     Brook- COMPLETED

      Birch Place- COMPLETED

     Crescent from Birch to Commonwealth - COMPLETED

o    Paving

    Livingston Avenue - COMPLETED

               Brook- COMPLETED

                Birch Place- COMPLETED

     Crescent from Birch to Commonwealth- COMPLETED


    November 2nd - Paving

    Central Avenue 

    Stoneridge


    November 3rd - Paving

o    Possum Way - TBD

o    Southgate/Ryder Way - SCHEDULED FOR 11/3 AND 11/6


    November 9th - Milling

o    Jones Drive

o    Princeton Drive


    November 10th - Paving

o    Jones Drive

o    Princeton Drive