PSE&G has completed the gas main upgrades in several neighborhoods. Now that the ground has settled, they will begin to restore roads with permanent paving. Please see below for the milling and paving schedule. This schedule will be adjusted in the event of inclement weather.
The milling and paving activities will occur during daytime hours between 7:00 a.m. and 6:00 p.m. Work is scheduled to begin in the next couple of weeks, weather permitting. Please abide by all emergency “No Parking” signs, as they will be posted 24 hours before work is scheduled to begin on each street.
The goal is to complete this work with minimal impact to your neighborhood. Police will be directing traffic, and residents will be able to drive on the roads during non-paving hours.
• October 18th - Milling - COMPLETED
o Surrey Lane
o Darby Court
o Salt Brook
• October 19th - Milling
o Charnwood Road - COMPLETED
o Edward Court - COMPLETED
o Crescent Drive - COMPLETED
o Livingston Ave - COMPLETED
• October 20th - Milling
o Livingston Avenue
o Central Avenue
• October 23rd - Milling
o Central Avenue
o Stoneridge
• October 24th
o Milling
Southgate/Ryder Way
• October 25th
o Milling
Southgate/Ryder Way
o Paving
Edward Court - COMPLETED
Brook
Park Place
Crescent Drive
Livingston Avenue
Surrey Lane - COMPLETED
Darby Court - COMPLETED
Salt Brook - COMPLETED
Charnwood Road - WILL BE COMPLETED by end of day on 10/25
• October 26th
o Milling
Possum Way
Southgate/Ryder Way
Brook
Birch Place
Crescent from Birch to Commonwealth
o Paving
Livingston Avenue
Central Avenue
Stoneridge
Brook
Birch Place
Crescent from Birch to Commonwealth
• October 27th - Paving
o Possum Way
o Southgate/Ryder Way
o Brook
o Birch
o Crescent from Birch to Commonwealth
• October 30th - Paving
o Possum Way
o Southgate/Ryder Way
• November 9th - Milling
o Jones Drive
o Princeton Drive
• November 10th - Paving
o Jones Drive
o Princeton Drive