Riverview Paving will be in the borough for approximately 3 weeks. Milling is scheduled to take place from Tuesday, July 30 through August 8. Paving is scheduled to begin the week of August 12. All dates are weather dependent. See borough website for complete schedule and any updates.
Road Milling Beginning on July 30 and 31:
| Street | Between Street 1 | Between Street 2 | Milling Date(s) |
Pittsford Way | Elkwood
| Springfield
| 30-Jul
|
Madison
| Commonwealth
| Elkwood
| July 30 & 31
|
Edgewood
| Commonwealth
| Walton
| 31-Jul
|
Tall Oaks
| Division Ave
| Stoneridge
| 31-Jul
|
Club Dr
| Countryside
| Club Lane
| July 31 & August 1
|